Owing to the city's income
from the work of the Municipal Electric Facilities (MEF) in 1896-1905, Lviv
Magistrate decided to expand its tram routes and the electricity supply
network. Electric lighting of the houses became more and more desirable among
the Lviv residents. However, the carrying capacity of the city's direct current
grid reached its limit already in 1902. The DC power plant on Wulecka street (today,
vul. Sakharova) was designed to connect, apart from the tram, 6,000 lamps with
a capacity of 50 W each, that is, 300 kW. In 1905, the total connected capacity
of the DC electric grid consumers was already 316 kW, and by 1908 it reached
490 kW, that is, much more than its optimal occupancy. The further expansion of
the DC grid to the distant parts of the city was not reasonable because of the
inability to provide the necessary voltage level.
Józef Tomicki, director of the
MEF in 1897-1925, recalled, "the tram routes and the electricity network
covered only certain parts of the city, so remote suburbs quite rightly sought
means of transport communication and electrification of their homes." In
1905 the Magistrate instructed him to work out technical and financial
possibilities for the implementation of new plans. Only 4 million crowns were
allocated for the expansion of the existing power plant and network, though.
In despair Józef Tomicki sought
support from Roman Dzieślewski, a professor at the Lviv Polytechnic and a
permanent member of the Municipal Electricity Commission. Their collaboration
or rather an engineering adventure in 1906, yielded results. Having Dzieślewski's
support in advancing the alternating current idea, Tomicki suggested that the
Magistrate should send the project to Vienna for a technical audit. The
Magistrate asked Alex Kern, the former director of the Lviv electric tram in
1894-1897, to lead the examination. Tomicki previously spoke with Kern about
his problems. Kern recalled that he had discussed with Tomicki the possibility
of using the existing DC cable lines for the 110 V AC grid, as well as the
groundwork done by the MEF with respect to the construction of new power
plants. In these materials, Tomicki and the MEF directorate considered two
sites for a future power plant: at Bilohorshcha, 7 km from the city, for the
construction of a three-phase current power plant, and the Pełczyński lakes for
DC power plants.
At the suggestion of Roman
Dzieślewski, a special committee was set up to expand the MEF, which, in
addition to Roman Dzieślewski, included Józef Tomicki and Alex Kern. At a
meeting of the committee on 10 October 1906, a decision was reached to abandon
the direct current system. The remoteness of the power plant on Sakharova
street from the railway was put forward, as it complicated the fuel supply.
Alex Kern suggested building a new AC power station at Persenkówka, a suburban
area, near the Lviv-Stanislaviv-Chernivtsi railway track. The committee
appealed to the Magistrate with a budget of 11.8 million crowns, much more than
previously anticipated. According to Tomicki, "the need to expand the MEF
was becoming more and more obvious and urgent, so the City Council finally
decided to provide the necessary loans for the amount of 10 million crowns, and
when this amount was spent in the course of works, another amount of 4 million
was added, 14 million crowns in total." On 30 November 1906, the Magistrate
appealed to the Viceregency apropos of a project to expand the electric tram in
Lviv. Józef Tomicki was the spokesman, while Roman Dzieślewski took part as
well. At this meeting, a final positive decision was taken. Intensive work
began. In November 1908, the first two generators with a capacity of 1500
horsepower (hp) each were delivered to Lviv from the Škoda plant in Plzen, and
the official consecration of the new power plant took place on 18 February
1909. The total capacity of the power plant was 6000 hp or 4500 kW.
Initially, the Lviv power
plant was supplied with fuel oil from Boryslav. In 1913 Józef Tomicki suggested
replacing this expensive fuel with coal. His memorandum for the Magistrate
dated 10 May 1913 is kept in the State Archive of Lviv Region, containing a
detailed description of the necessary equipment and the calculation of payback.
In 1914 the power plant was switched over to coal imported from Silesia. Both
types of fuel did not satisfy the Lviv city leaders in terms of environmental
safety. Rare trees planted in the Stryiskyi Park suffered particularly. After the
gas pipeline Dashava-Lviv was built in the late 1920s, the power plant was switched
over to natural gas.
In 1913 two turbogenerators
with a total capacity of 6 MW and three steam engines with a capacity of 1.1 MW
were installed at the plant. Water for cooling was supplied from the Żelazna
woda (Zalizna Voda) springs and from the stream of Sofiówka (Sofiyivka).
During the battles for Lviv in November 1918,
the power plant and the city cable grid suffered damage. However, even in the
hard time of an armed confrontation, there were conscious people on both sides,
who considered the safety of civilians and their right to a decent life,
including the uninterrupted supply of electricity to the city, to be above all.
On 19 November 1918, at 10 a.m., captain Osyp Bukshovanyi, a representative of
the Ukrainian army command, and Ludwik de Laveaux, a Polish commanding officer,
made an agreement according to which the power plant at Persenkówka and the
gas station on Źródlana (now Dzherelna) street were declared extraterritorial.
Joint commissions consisting of three Ukrainian and three Polish
representatives were present at these municipal enterprises constantly.
From November 1918 till May
1919, the power plant did not produce energy. Apart from the damage, emergency
blackouts in the city's power grid added to this. Cable lines and transformer
substations were also damaged because of street fighting. According to the
memoirs of Józef Tomicki, as early as eight days after the ceasefire, the power
plant was repaired and put into operation. Its capacity was constantly
increasing and reached 19500 kW in 1925.
All suburban villages were to
be included into Lviv in 1930. It was considered thus to convert the power plant
into a regional one, and to construct electric lines to the towns of Żółkiew (Zhovkva),
Jaworów (Yavoriv) and, most importantly, to the water pumping stations. As electric
pumps were installed at the station in Karaczynów (Karachyniv) and at the wells
in Wola Dobrostańska (Volia Dobrostanska), Szkło (Shklo) and Wielkopole
(Velykopole) it became possible to
provide Lviv with water all round the clock.
The power plant's
modernization could not keep pace with the accelerating expansion of the
electricity grid. It was more a question
of distributing equipment, rather than the generating one. All 5 kV equipment
was designed for a maximum capacity of 4.6 MW. The grid reached such a capacity
in 1921, and in 1925 the total consumption became 7.1 MW. Lviv Magistrate invited
the Warsaw power plant's director to conduct an audit of the MEF in regard to
their profitability. He noted in the report dated 27 February 1928 that,
"taking into consideration the example of large European cities, I can say
that electricity consumption in Lviv will grow, and one of the factors
restraining this process will be the 5 kV distributing equipment, which is
completely worn out and in critical condition. The importance of its
replacement can be emphasized by the explosion of an oil switch at the power
plant in Chorzów."
During 1929, the 5 kV
distributing equipment and the power plant's control panel were transferred to
a new building; old switches were replaced by new ones made by the
Siemens-Schuckert company.
In 1932 the electrification of
localities outside Lviv started, and the power-producing capacity of the power
plant was increased to 26 MW.
Retreating in 1944, the
Germans removed three turbogenerators from the power plant. Two of them, with a
total capacity of 12.4 MW, were in the best condition among the five available
at the beginning of the war. The third one, completely new, with a capacity of
16 MW, was established during the Nazi occupation. Besides, two transformers
5/30 kV, which transmitted electricity to the Lviv district 30 kV grid, were
taken from the power plant and sent to Germany. The rest of the equipment and
facilities were destroyed by explosions of nine high-explosive bombs laid by
the Nazis in various places of the power plant. The explosion damaged
generating equipment and burnt three cooling towers. Approaches to the power
plant were mined.
As of 27 July 1944, when the
Soviet troops captured Lviv, the municipal power plant did not work. Lviv and
the region remained virtually without light. 12 days later, on 8 August 1944, a
0.5 MW turbogenerator was put into operation, and by the end of the year a 0.5
MW railway mobile power plant was delivered. As a result of the destruction, at
the end of the Second World War the total capacity of the Lviv power plant
decreased from 40 MW (6 generators) to 1 MW as of 1 January 1945.
To settle the urgent issue of
restoring generating capacity, equipment was brought from a German power plant
as a contribution for the damage incurred during the war.
The transitional base of
trophy power plant equipment was located in Lviv in four different places with
a total area of over 15 hectares. The equipment was unloaded and loaded by
electrical supply network workers, military men and German prisoners of war.
The equipment delivered to the Lviv component base was then transported to
various Soviet power plants. Blechhammer power plant's equipment was sent to
the Chelyabinsk heating plant, from the area of Heydebreck — to the heating
plant in Lysychansk, from Krapets (an unidentified locality mentioned in
archival documents) — to the Zuyivska heating plant, from the town of Oświęcim — to the heating plant in
Kemerovo, from the Wilhelm and Walter electric power stations — to the
Shterivska power plant. At the Lviv power plant, there was equipment taken from
the power plant in Odertal (Deschowitz-Beuthen/Zdzieszowice).
In 1945, to compensate the
lack of electricity, the city had to supply it from the Drohobych power plant
using a 110 kV line. In the same year, 12 MW trophy generating equipment was
established at the Lviv power plant and three General Electric railway mobile
power plants were delivered, with a total capacity of 7.5 MW.
Restoring the generation of
electricity was to be done without delay. To stimulate the workers, the manager
of the Lviv Energy Complex Oleksiy Kucheruk appealed to the People's
Commissariat of Power Plants of the USSR to allow him to give them "4,000
liters of vodka, 100 kilograms of tobacco and 10,000 coupons for an additional
second hot meal", which, during the postwar period of total deficiency,
was a very important argument for the workers.
In 1946 two more
turbogenerators with a capacity of 12 MW and 4 MW were put into operation at
the Lviv power plant.
Now, there was not enough
water at the power plant. In 1946-1948, a reservoir on the Shchyrets river was
built in the village of Navariya (today it is the Hlynna Navariya lake), from
where a water supply system was to deliver water to the Lviv power plant. Various
doers were involved: geologists came from Kharkiv; drilling equipment was
brought from there as well; nails and bolts came from Dnipropetrovsk (now
Dnipro), cement was from Zdolbuniv, and coal came from Stalino (now Donetsk).
During 1949 the installed
capacity of the Lviv power plant increased to 45.5 MW. Gas supplied from the
Dashava gas field covered 91% of the fuel needs, and 9% were covered by coal
from Silesia.
The maximum power of 60 MW was
reached by the Lviv power plant in the late 1950s. After the construction of
the 700 MW Dobrotvir power plant, the value of the Lviv power plant for the
power supply of the region decreased and in 1960 it was switched over to the
heating mode (Lviv heat and power plant 1). It is from this plant that the
residents of the areas of Naukova and Volodymyra Velykoho streets, Sykhiv and
Novy Lviv are supplied with heat and hot water. At present, the plant functions
in the "cogeneration" mode (simultaneously produces thermal and electric
energy), which is considered the most economical use of fuel resources.